AGENDA ITEM EXECUTIVE SUMMARY | Item number: 5.g | |
| Title: | Ordinance Granting Approval of a Zoning Map Amendment, Special Use for Planned Unit Development and PUD Preliminary Plan for Seventh Street Commons |
||
| Presenter: | Russ Colby | ||
| Meeting: Committee of the Whole | Date: October 19, 2026 | ||
| Proposed Cost: $N/A | Budgeted Amount: $N/A | Budgeted: N/A | |
| TIF District: | |||
| Executive Summary (if not budgeted, please explain): | |||
The subject property is the 27-acre property known as the “Applied Composites” or “Lexington Club” site, located northwest of downtown, north of Dean/State Streets between N 5th and N 12th Streets, and south of the former railroad tracks.
Comprehensive Plan After the Applied Composites business closed and vacated the site in 2005, the City approved a Comprehensive Plan amendment to change the site to residential land use, to be an extension of the neighborhood to the south. The 2013 Comprehensive Plan future land use map identifies single-family attached residential (townhomes) west of 9th Street, and single family detached east of 9th Street. The property is currently zoned for residential land uses (RT-3 & RM-2) based on the 2013 Lexington Club plan, which was never constructed. The site has been vacant since 2005.
The proposal for Seventh Street Commons generally complies with the City’s Comprehensive Plan land use recommendations and aligns with the City’s efforts of the past 20 years to see the underutilized site cleaned up, redeveloped for residential use and interconnected with the neighborhood to the south.
Proposal Pulte Home Company is proposing to develop the subject property with a 105-unit residential subdivision. The proposal is similar to a Concept Plan reviewed by the City earlier this year.
Applications requesting Zoning Map Amendment, Special Use for Planned Unit Development (PUD) and PUD Preliminary Plan have been submitted by Pulte. Details of the proposal:
Plan Commission Review – Plan Commission held a public hearing on 9/22/26. Ten members of the public spoke at the public hearing or provided written comment. Comments centered around concerns for change to neighborhood character, impact on property values and taxes, removal of trees, and traffic impacts. Plan Commission recommended approval by a vote of 7-0, subject to the following conditions:
The applicant has provided revised plans in response to the Plan Commission conditions. All conditions have been addressed on the plans that are attached to the approval Ordinance.
Affordable Housing Units The developer evaluated incorporating affordable units into the project. However, the cost gap was too significant to be covered by any City fee waiver or grant, and there is no opportunity to increase the unit count and still have a primarily single-family project. Inclusion of affordable units within the project would require significant subsidy given the other extraordinary development costs of the project. The developer will provide payment of fee-in-lieu of providing affordable units per the amount required by ordinance.
Although this project does not add to the City's affordable housing supply, this project represents a unique opportunity to add a substantial number of new single-family homes to the market within an infill location.
Traffic Study The developer prepared a traffic study that was reviewed by the City’s engineering consultants, who found that overall traffic in the surrounding neighborhood will not be negatively affected due to multiple connections dispersing traffic over various routes. When traffic from the new development does affect traffic in the surrounding neighborhood, the impacts will be minimal, such as wait-times being increased by a second or two at an intersection. Our consultant engineers requested some minor modifications to the study to ensure it is complete and accurate, and the developer recently submitted an updated study that includes those modifications. This updated study is currently being reviewed, and staff do not anticipate any substantial difference in the projected traffic impacts once the study is finalized.
Financial Assistance The City is in the process of establishing a Tax Increment Financing (TIF) District on the property. TIF will be utilized to cover the City’s costs to relocate electric distribution infrastructure running through the property, which is in conflict with development of the site. The total amount of TIF expense is anticipated to be less than $3 million. All other development costs are to be borne by the developer, including demolition, site work and environmental remediation. |
|||
| Attachments (please list): | |||
| Recommendation / Suggested Action (briefly explain): | |||
Recommendation: Approve |
|||