Julian Lee, Director of Public Works
Michael Vartanians, City Engineer
Bassam AL-Beitawi, Transportation Program Manager
CONSIDERATION OF THE AWARD OF A CONSTRUCTION CONTRACT TO DBX, INC. IN AN AMOUNT NOT TO EXCEED $16,069,567.00 FOR THE NORTH SOUTH CORRIDOR INTELLIGENT TRANSPORTATION SYSTEMS DEPLOYMENT ON FAIR OAKS AVENUE PROJECT RABA01-5071 (024)
It is recommended that the City Council:
- Award a construction contract (Attachment No. 1) to DBX, Inc for construction services for the North South Corridor Intelligent Transportation Systems Deployment on Fair Oaks Avenue Project RABA01-5071 (024) (Project) in an amount not to exceed $16,069,567.00 including the proposed bid amount of $13,391,305.90 and a 20% contingency of $2,678,261.10;
- Reject all other bids received;
- Authorize the City Manager to execute the Contract and all related documents, in final form approved by the City Attorney.
The Fair Oaks Avenue Intelligent Transportation Systems (ITS) Deployment Project (Project) will improve traffic operations, safety, and pedestrian accessibility along Fair Oaks Avenue between Huntington Drive and Columbia Street. The Project includes traffic signal upgrades, new traffic management technology, pedestrian crossing improvements, and modifications to existing intersections.
The Project design has been completed, and staff is requesting City Council approval of the construction contract to initiate construction. The estimated total Project cost is $18.2 million, funded through federal Rogan funds, local funds, and LA Metro Measure R funds.
On August 12, 2004, the City of South Pasadena was awarded $ 9,343,000 in Federal Highway Administration (FHWA) Rogan Funds (Bill No. HR 5394) for the construction of the SR-110 ramp. The project was not implemented because of right-of-way constraints and lack of technical studies and data.
In November 2019, FHWA and the California Department of Transportation (Caltrans) notified the City that the federal funds were at risk of expiring unless the project proceeded. To preserve the funding, City staff coordinated with FHWA and Caltrans to revise the project scope to focus on reducing traffic congestion and improving traffic operations along Fair Oaks Avenue between Huntington Drive and Columbia Street. Through continued coordination, the City successfully extended the federal funding expiration date to June 30, 2027.
On August 18, 2021, the City Council awarded a professional services agreement to KOA for engineering design services for the Project. As the design progressed, additional traffic engineering and Intelligent Transportation Systems (ITS) expertise was needed to complete the proposed improvements.
On July 16, 2025, the City Council approved a professional services agreement with Iteris, Inc. to provide traffic engineering and ITS support services. Subsequently, on March 4, 2026, the City Council approved an amendment to the agreement with Iteris to complete the Project's design plans.
The Project plans and specifications were prepared by registered professional engineers with Iteris, Inc. and Kimley-Horn and Associates in accordance with current professional engineering standards. The City Engineer has reviewed the plans and specifications and determined that the proposed design is reasonable and meets applicable engineering standards. Accordingly, the City Council approved the plans and specifications at their October 21, 2026 meeting.
The Fair Oaks Avenue Intelligent Transportation Systems (ITS) Deployment Project (Project) will improve traffic operations, safety, and pedestrian accessibility along Fair Oaks Avenue between Huntington Drive and Columbia Street. The Project includes traffic signal upgrades, new traffic management technology, pedestrian crossing improvements, and modifications to existing intersections.
The proposed scope of work includes:
- Traffic Signal Improvements: Installation of new traffic signal equipment at 11 signalized intersections along Fair Oaks Avenue, including Columbia Street/Raymond Hill Road, State Street/Grevelia Street, Hope Street, Mission Street, El Centro Street, Oxley Street, Monterey Road, Bank Street, Rollin Street, Oak Street, and Huntington Drive.
- Traffic Management Technology: Installation of traffic monitoring cameras, emergency vehicle preemption systems, and Intelligent Transportation Systems (ITS) equipment to improve traffic management and emergency response.
- Pedestrian Safety Improvements: Installation of Rectangular Rapid Flashing Beacons (RRFBs) at Fair Oaks Avenue and Spruce Street, upgrades to existing curb ramps to meet Americans with Disabilities Act (ADA) requirements, and modifications to existing curb extensions where necessary to improve accessibility.
- Intersection Modifications: Closure of Grevelia Street at Fair Oaks Avenue and closure of the existing slip lanes at Fair Oaks Avenue and Huntington Drive to improve intersection operations and safety.
- Additional Infrastructure Improvements: Installation of new internally illuminated street signs and fiber optic communication infrastructure connecting City Hall to the Public Works Garfield Yard.
Staff is also coordinating with the South Pasadena Arts Council (SPARC) to develop a plan for the removal of the existing painted traffic signal cabinets impacted by the Project. Following completion of construction, staff will work with SPARC to invite local artists to repaint the traffic signal cabinets, continuing the City's efforts to incorporate public art into the community.
Procurement Process
South Pasadena Municipal Code (SPMC) Chapter 2 Administration, Article XI describes the City's purchasing rules. Specifically, SPMC Section 2.99-39 defines the purchasing procedure to award a Public Works Contract to the lowest responsible bidder. Contracts resulting from competitive bidding are awarded based on the lowest responsible bidder who submitted a bid that was responsive to the solicitation request. A bid is considered to be responsive if it conforms in all material respects to the solicitation requirements, and a bidder is considered to be responsible if they possess the demonstrated ability, capacity, experience and skill to provide the goods and/or services required by the solicitation.
The Public Works Department solicited bids from contractors through a Notice Inviting Bids posted on the PlanetBids website on October 8, 2026. The Notice Inviting Bids was also published in the South Pasadena Review on October 9, 2026. The advertisement included the plans, specifications, and other contract documents. Two hundred and eighty-three (283) firms were notified of the proposal opportunity through PlanetBids.
Proposals were received through November 9, 2026, from the following six (6) firms:
| Bidder No. | Bidder | Bid Amount |
| 1 | DBX, Inc | $13,391,305.90 |
| 2 | Alfaro Communications Construction Inc. | $13,443,387.85 |
| 3 | Crosstown Electrical & Data, Inc. | $15,587,573.00 |
| 4 | Elecnor Belco Electric, Inc. | $15,699,000.00 |
| 5 | PTM General Engineering Services | $16,420,553.20 |
| 6 | California Professional Engineering, Inc. | $16,809,159.95 |
Recommended Award
DBX, Inc. is located in the City of Temecula, California and is the lowest responsive bidder. DBX, Inc has previously performed similarly scoped work in the City of Norwalk successfully. Reference checks to the City of Norwalk provided excellent reviews of workmanship and contractor conduct. They have extensive experience in traffic signal equipment replacement and civil street improvements and have a General Engineering (A) and an Electrical (C-10) license by the State of California Contractors State License Board. Therefore, staff recommends that the City Council award a construction contract to DBX, Inc. for construction services for the Project not to exceed $16,069,567.00.
Construction is anticipated to begin in early 2027, with completion scheduled for winter 2028.
Funding for this project is included in the FY 2026-2027 Budget under the N-S Fair Oaks ITS Project (No. 9161) account strings. The total estimated Project cost is approximately $18.2 million, consisting of the following:
| Activity | Expenditure | Funding Amount | Funding Source |
| Design | $1,300,000 | $1,300,000 | Local Prop C Funds (Fund 207) |
| Construction Management/Inspection | $758,526 | $671,523.07 | Rogan Funds (Fund 214) |
| $87,002.93 | Measure R LR (Fund 233) | ||
| Construction (Engineer's Estimate) | $16,069,567 | $8,672,039.93 | Rogan Funds (Fund 214) |
| $7,397,527.07 | Measure R MIP (Fund 243) | ||
| Project Total: | $18,143,526 | ||
The Project is funded through approximately $9.34 million in federal Rogan funds, local matching funds, and $10 million in LA Metro Measure R funds. These funding sources are anticipated to be sufficient to complete the Project. As noted above, the utilization of the funds is anticipated to be $1,300,000 in Local Prop C Funds (Fund 207), $9,343,563 in Rogan Funds (214), $87,002.93 in Measure R Local Return (Fund 233) and $7,397,527 in Measure R MIP (Fund 243).
The federal Rogan funds are currently scheduled to expire on June 30, 2027. Since construction is anticipated to extend beyond this date, staff has reached out to Caltrans to request an extension following the selection of a construction contractor. Measure R funds are available to supplement the federal funding and address potential construction cost increases. Any unused Measure R funds may be considered for reallocation to other eligible projects in coordination with LA Metro.
This item is related to street improvement goals, traffic mitigation and safety goals in the City Council's 2026 compilation of priorities.
The Project was discussed with the Public Works and Infrastructure Commission (PWIC) Mobility on August 27, 2025 and May 13, 2026.
The public was made aware that this item was to be considered this evening by virtue of its inclusion on the publicly noticed agenda and posting of the same agenda and reports on the City’s website.
The Project meets the requirements of California Environmental Quality Act Guidelines Section 15301 for Class 1, Existing Facilities, as the Project is consistent with Sections 15301(c) and 15301(d) listed. The City posted a Notice of Exemption with the State Clearinghouse on October 23, 2025, and with the Los Angeles County Registrar Clerk Recorder on October 30, 2025.