Nick Kimball, Assistant City Manager/CFO
DISCUSSION AND DIRECTION RELATED TO THE DEVELOPMENT IMPACT FEE STUDY AND CONSIDERATION OF ESTABLISHING ALTERNATIVE INFRASTRUCTURE FINANCING DISTRICTS, INCLUDING EVALUATION OF AN ENHANCED INFRASTRUCTURE FINANCING DISTRICT FOR THE MISSION STREET AND FAIR OAKS AVENUE COMMERCIAL DISTRICT
It is recommended that the City Council:
- Receive and file a status presentation and update on the Development Impact Fee Nexus Study (Attachment 1);
- Receive an informational presentation regarding Alternative Infrastructure Financing Districts, including Enhanced Infrastructure Financing Districts, Community Facilities Districts, and Assessment Districts (Attachment 2); and
- Discuss and provide direction, as appropriate.
In November 2025, the City Council approved an agreement with Willdan Financial Services to prepare a Development Impact Fee (DIF) Nexus Study to update the City’s development impact fees, which have not been comprehensively updated in over a decade. Staff is working with Willdan to complete outstanding data items before the draft Nexus Study is finalized. Staff is providing a status update prior to proceeding toward City Council consideration of adoption in March 2027.
Development impact fees may only fund the share of new facilities attributable to new development. They cannot fund existing facility deficiencies, maintenance, or operations. To address capital needs that impact fees cannot fund, staff and the City’s economic development consultant, Kosmont Companies, have evaluated alternative infrastructure financing districts, including Enhanced Infrastructure Financing Districts (EIFDs), Community Facilities Districts (CFDs), and Assessment Districts. Each approach differs in its revenue source, approval requirements, eligible uses, and effect on property owners and the General Fund.
After reviewing the trade-offs, staff recommends further evaluation of an EIFD encompassing the Mission Street and Fair Oaks Avenue commercial districts. Staff is requesting City Council direction on both items.
On September 27, 2023, the City Council adopted the General Plan and Downtown Specific Plan, which provides zoning to accommodate up to 2,775 residential units and 430,000 square feet of non-residential space.
On September 25, 2025, the City issued a Request for Proposals for a Development Impact Fee Nexus Study.
On November 19, 2025, the City Council approved a professional services agreement with Willdan in an amount not to exceed $56,040.
In January 2026, Kosmont Companies, under the City’s on-call real estate, financial advisory, and economic development services agreement, prepared a draft Infrastructure Financing District Analysis Summary evaluating the potential use of an EIFD and/or CFD in South Pasadena (Attachment 2).
The FY 2026-27 Adopted Budget includes updating the City’s development impact fees and exploring EIFDs and CFDs as one of four strategic focus areas and is part of the Finance Department’s Work Plan.
On September 3, 2026, Willdan provided initial draft impact fee tables for staff review and feedback.
On October 29, 2026, the Finance Commission received an informational report on economic development tools, including development impact fees, EIFDs, and CFDs.
- Public Safety Facilities: Police and fire facilities, vehicles and equipment, including a potential new fire station in the Monterey Hills area
- General Government Facilities: City Hall, Public Works yard, and Library/Senior Center Complex
- Parkland Acquisition: Acquisition of parkland (Quimby Act in-lieu fee for subdivisions; Mitigation Fee Act fee for infill development)
- Park and Recreation Improvements: Park improvements and recreation facilities
- Transportation Facilities: Bicycle Master Plan, capital improvement, and Systemic Safety Analysis Report projects
- Parking In-Lieu Fee: Public parking facilities, paid in lieu of providing required on-site parking
- Projects new development through the planning horizon;
- Sets a facility standard based on existing conditions and service level;
- Identifies the facilities needed to serve new development and what they cost; and
- Divides those costs among land uses based on the demand each type of development creates.
- Planning Horizon and Growth Projections. The study measures population growth from 2026 to buildout of the General Plan using data from the California Department of Finance, Certified Housing Element, Downtown Specific Plan, Census Data, the City’s adopted Capital Improvement Plan, and various Master Plans (e.g. Park Master Plan, Water/Sewer Master Plan, Library Master Plan, etc.).
- Service Population, Occupancy and Unit Size. Demand for public safety and general government facilities is measured by service population. Service population counts each resident as well as each worker at 0.31 of a resident, based on a 40-hour work week out of 128 non-work hours.
- Facility Valuation. Existing facilities are valued at what it would cost to replace them today including land, buildings, contents, vehicles, and information technology. New facilities use current replacement costs with an escalator for future development. Data is sourced from the County Assessor’s Office, insurance valuations, appraisals and other building valuation sources.
Demographic study for population growth. Per-capita costs drive the Public Safety, General Government, and park fees. Typically, population growth, occupancy and unit size projections are taken from Census (2023 American Housing Survey) and Southern California Association of Governments (SCAG) data. However, since state and local housing and density laws enacted since 2023 are not factored into Census data, specifically Measure SP and SB 79, staff engaged MIG to prepare a demographic study that provides min-mid-max population, occupancy, and unit size projects based on current data.
Per-square-foot construction costs. The draft tables currently have a wide range of per square foot replacement value for existing and planned City buildings. Willdan has requested current construction cost estimates, including soft costs, to provide a more realistic and consistent value for existing and planned facilities. Staff is working to obtain these estimates.
| Timeframe | Activity |
| November - December 2026 | Complete construction cost estimates and demographic study; Willdan prepares Parking In-Lieu Fee analysis; staff completes review of draft tables and project lists |
| January 2027 | Complete Draft Nexus Study; |
| February 2027 | Draft Nexus Study made available to the public and notice of public hearing issued (at least 30 days prior to hearing) |
| March 2027 | City Council public hearing to consider adoption of the Nexus Study, fee resolution, and related Municipal Code amendments |
| May 2027 | Fees take effect (no sooner than 60 days after adoption, per Government Code Section 66017) |
| EIFD | CFD | Assessment District | |
| Revenue source | Share of future property tax growth; no new tax | New special tax on property | New assessment on property |
| Approval | Public hearings; majority protest; no vote | Two-thirds vote of voters or landowners | Weighted majority property owner ballot |
| Eligible uses | Capital facilities of communitywide significance; maintenance; affordable housing | Capital facilities and certain services | Improvements and services providing special benefit |
| Revenue timing | Grows with development and reassessment; limited in early years | Available immediately upon levy | Available immediately upon levy |
| Effect on General Fund | Dedicates a share of future City property tax growth to the district | None | City pays the general benefit share and assessments on City parcels |
| Key considerations | County participation subject to County policy; administrative and reporting requirements | Two-thirds approval is difficult in developed areas with many owners and residents | Special benefit analysis is subject to legal challenge |
- Modify the development fee categories. The City Council may provide direction to add, remove, or combine development fee categories.
- Pursue additional study of alternative infrastructure financing districts. The City Council may direct staff to evaluate a CFD or assessment district instead of, or in addition to, an EIFD. Each would require voter or property owner approval and impose a new tax or assessment.
- Take no action on financing districts. The DIF study would proceed with the current draft development fee categories, and capital needs not funded by impact fees would continue to rely on the General Fund, grants, and other sources.
Updating the City’s development impact fees and exploring alternative infrastructure financing opportunities is part of the Finance Department’s FY 2026-2027 Adopted Work Plan. There is no direct fiscal impact associated with providing direction on this item.
Additional costs for further EIFD, CFD, or Assessment District analysis by Kosmont, along with all related district formation costs, will be estimated and presented to the City Council with a future contract amendment to expand the scope of the agreement with Kosmont and the Resolution of Intention to establish a district.