Item Number: 7.b.
City of Iowa City Logo
October 20, 2026

Resolution setting a public hearing on November 2, 2026 on project manual and estimate of cost for the construction of the Annual ADA Curb Ramps 2026 project, directing City Clerk to publish notice of said hearing, and directing the City Engineer to place said project manual on file for public inspection.


Prepared By:

Vivienne Olsson – Civil Engineer

 
Reviewed By:

Jason Havel – City Engineer
Ron Knoche – Public Works Director
Geoff Fruin – City Manager

Liz Craig - Assistant City Attorney

 
Fiscal Impact:

$160,000 available in the Annual ADA Curb Ramps Account #S3822.

 
Staff Recommendation:
Approval
 
Attachments:
Resolution
 
Executive Summary:

This agenda item begins the bidding process for the Annual ADA Curb Ramps 2026 project. This project generally includes the removal and replacement of ADA curb ramps and sidewalk and full depth pavement patches.

Background / Analysis:

The Annual ADA Curb Ramp 2026 project locations are:


•    Jacque Street & Shannon Drive
•    Bluffwood Circle & Stuart Court
•    Westbury Court & Westbury Drive
•    Lower West Branch Road & Westbury Drive
•    Alpine Drive & Brookside Drive
•    Hollywood Boulevard & Western Road
•    Grantwood Street & Hollywood Boulevard
•    Clark Street & Walnut Street

 

Project Timeline:

Set Public Hearing – October 20, 2026
Hold Public Hearing – November 2, 2026
Bid Letting – December 1, 2026
Award Date – December 8, 2026
Construction – April 2027 to June 2027