$160,000 available in the Annual ADA Curb Ramps Account #S3822.
This agenda item begins the bidding process for the Annual ADA Curb Ramps 2026 project. This project generally includes the removal and replacement of ADA curb ramps and sidewalk and full depth pavement patches.
The Annual ADA Curb Ramp 2026 project locations are:
• Jacque Street & Shannon Drive
• Bluffwood Circle & Stuart Court
• Westbury Court & Westbury Drive
• Lower West Branch Road & Westbury Drive
• Alpine Drive & Brookside Drive
• Hollywood Boulevard & Western Road
• Grantwood Street & Hollywood Boulevard
• Clark Street & Walnut Street
Project Timeline:
Set Public Hearing – October 20, 2026
Hold Public Hearing – November 2, 2026
Bid Letting – December 1, 2026
Award Date – December 8, 2026
Construction – April 2027 to June 2027