BOARD MEMBERS:

DISTRICT 1 - Dom Zanger
DISTRICT 2 - Kollin Kosmicki
DISTRICT 3 - Mindy Sotelo
DISTRICT 4 - Angela Curro
DISTRICT 5 - Ignacio Velazquez
San Benito Logo

Agenda Item
Regular Meeting of the
Board of Supervisors
Tuesday, September 15, 2026

Website:
www.sanbenitocountyca.gov
COUNTY EXECUTIVE OFFICER:
Esperanza Colio Warren

COUNTY COUNSEL:
Gregory P Priamos

CLERK OF THE BOARD:
Vanessa Delgado
 

Item Number: 1.18
MEETING DATE:
09/15/2026
 
DEPARTMENT:
RESOURCE MANAGEMENT AGENCY
 
AGENDA ITEM PREPARER:
Salman Kazmi
 
DEPT HEAD/DIRECTOR:
Deems Katada
 
 
SUBJECT:


PUBLIC WORKS DEPARTMENT - A. GONZALEZ
1. Approve addition of the District Attorney's Office Second Floor Interior Improvements Project to the FY 2026–27 Capital Improvement Program; and
2. Approve a total project budget of $53,000.00 for the District Attorney’s Office Second Floor Interior Improvements Project; and

3. Adopt FY 26/27 Budget Amendment Resolution transferring $45,000.00 from the District Attorney Asset Forfeiture Fund and $8,000.00 from the Maintenance Budget to the Capital Improvement Project.
SBC FILE NUMBER: 105.3
RESOLUTION NO. 2026-124

 
AGENDA SECTION:


CONSENT AGENDA

 
BACKGROUND/SUMMARY:


The District Attorney's Office is located on the second floor at 419 Fourth Street, Hollister, California. The building was constructed in 1996, and the existing second-floor carpet is original to the facility. After approximately 30 years of continuous use, the carpet has exceeded its expected useful life and has experienced significant wear and deterioration due to age and daily use. Recent evaluations also identified localized areas of deteriorated subflooring that require repair prior to the installation of new flooring. Addressing these deficiencies as part of the project will help prevent future flooring failures, extend the service life of the new flooring system, and reduce long-term maintenance costs.

 

The proposed project includes the replacement of approximately 4,068 square feet of carpet, replacement of bathroom vinyl flooring within the project area, localized subfloor repairs, HAZMAT assessment, incidental plumbing materials, project management, and a contingency to address unforeseen conditions encountered during construction.

The County budgeted $350,000 in the FY 2026–27 Maintenance Budget (Budget Unit 101.70.1290) for emergency repairs and eligible CIP and maintenance needs. The total estimated project cost is $53,000, funded by $45,000 from the District Attorney Asset Forfeiture Fund (G/L Account 427.45.4420.1000) and $8,000 from the FY 2026–27 Maintenance Budget (Budget Unit 101.70.1290).

Because this project was not included in the adopted FY 2026–27 Capital Improvement Program, Board approval is requested to add the project to the FY 2026–27 CIP schedule, approve the project budget, and authorize the Chief Executive Officer or designee to execute the necessary budget adjustments, budget transfers, contracts, amendments, supplemental agreements, purchase orders, and other related project documents necessary to implement the project, provided total project expenditures do not exceed the approved project budget of $53,000.

 
FISCAL IMPACT:


The project budget of $53,000 will be funded from the following sources:

  • $45,000 from the District Attorney Asset Forfeiture Fund (G/L Account 427.45.4420.1000).
  • $8,000 from the Maintenance Budget (Budget Unit 101.70.1290), which includes funding designated for emergency repairs and eligible CIP and maintenance needs.
 
STAFF RECOMMENDATION:


1. Approve addition of the District Attorney's Office Second Floor Interior Improvements Project to the FY 2026–27 Capital Improvement Program; and
2. Approve a total project budget of $53,000.00 for the District Attorney’s Office Second Floor Interior Improvements Project; and

3. Adopt FY 26/27 Budget Amendment Resolution transferring $45,000.00 from the District Attorney Asset Forfeiture Fund and $8,000.00 from the Maintenance Budget to the Capital Improvement Project.

 
ATTACHMENTS:
Agenda Fact Sheet - DA Carpet Replacement Project
Budget Amendment Resolution - DA Office 2nd Floor Project
DA Office 2nd Floor TI Project - Cost Estimate