BOARD MEMBERS:

DISTRICT 1 - Dom Zanger
DISTRICT 2 - Kollin Kosmicki
DISTRICT 3 - Mindy Sotelo
DISTRICT 4 - Angela Curro
DISTRICT 5 - Vacant
San Benito Logo

Agenda Item
Regular Meeting of the
Board of Supervisors
Tuesday, November 3, 2026

Website:
www.sanbenitocountyca.gov
COUNTY EXECUTIVE OFFICER:
Esperanza Colio Warren

COUNTY COUNSEL:
Gregory P Priamos

CLERK OF THE BOARD:
Vanessa Delgado
 

Item Number: 1.7
MEETING DATE:
11/03/2026
 
DEPARTMENT:
RESOURCE MANAGEMENT AGENCY
 
AGENDA ITEM PREPARER:
Deems Katada
 
DEPT HEAD/DIRECTOR:
Adolfo Gonzalez
 
 
SUBJECT:


PUBLIC WORKS DEPARTMENT - A. GONZALEZ
1. Approve Amendment #1 for Granite Construction Company to modify name of the company as Papich Construction, Inc. has merged with and into Granite Construction Company (Granite) with Granite as the surviving corporation; and
2. Authorize the Chair, County Executive Officer, or designee to approve the Amendment.
SBC FILE NUMBER: 105.3

 
AGENDA SECTION:


CONSENT AGENDA

 
BACKGROUND/SUMMARY:


On March 20, 2025, County and Papich Construction Company, Inc. (Papich), Contractor’s predecessor by merger, entered into a contract for the County Project #PWB-2418, 2025 Job Order Contracting (JOC) – Class A License Engineering.
On September 9, 2025, County issued a Notice to Proceed to Papich for the San Juan Highway Rehabilitation Project, Project Number PWB-2520 (Project), in which scope of works had been completed sometime in June 2026.
Effective January 1, 2026, Papich merged with and into Granite Construction Company (“Granite”), with Granite as the surviving corporation. Accordingly, Granite is the successor to Papich under the original contract. All references in the original contract and Contract Documents to “CONTRACTOR,” “Contractor,” or Papich Construction Company, Inc. shall hereafter mean Granite Construction Company. Granite succeeds to all rights, duties, obligations, liabilities, warranties, indemnities, and other responsibilities of Papich arising under or relating to the original contract, including those arising from work performed before the effective date of the merger.
In order for Granite to be paid for the works being done for the Project, a contact amendment is necessary for the merger between Papich and Granite with Granite as the surviving corporation.

 
FISCAL IMPACT:


The San Juan Highway Project had been budgeted in FY2025-2026 and budget had been carried over to FY2026-2027.

 
STAFF RECOMMENDATION:


1. Approve Amendment #1 for Granite Construction Company to modify name of the company as Papich Construction, Inc. has merged with and into Granite Construction Company (Granite) with Granite as the surviving corporation; and
2. Authorize the Chair, County Executive Officer, or designee to approve the Amendment.

 