Agenda Item
Regular Meeting of the
Board of Supervisors
Tuesday, November 17, 2026

Website:
www.sanbenitocountyca.gov
COUNTY EXECUTIVE OFFICER:
Esperanza Colio Warren

COUNTY COUNSEL:
Gregory P Priamos

CLERK OF THE BOARD:
Vanessa Delgado
 

Item Number: 1.20
MEETING DATE:
11/17/2026
 
DEPARTMENT:
RESOURCE MANAGEMENT AGENCY
 
AGENDA ITEM PREPARER:
Ramesh Pandurangan
 
DEPT HEAD/DIRECTOR:
Adolfo Gonzalez
 
 
SUBJECT:


PUBLIC WORKS DEPARTMENT - A. GONZALEZ
1. Approve Amendment #2 with CM PROS to extend the contract term through June 30, 2027 with no changes to scope or cost to provide construction contract administration, engineering, inspection and environmental compliance services for the construction of the PWB-2402 Limekiln Road Bridge Over Pescadero Creek Bridge Replacement Project – Federal Aid Project No. BRLO-5943(063);  and
2. Authorize the Chair, County Executive Officer, or designee to execute the contract amendment.

SBC FILE NUMBER.: 105.3

 
AGENDA SECTION:


CONSENT AGENDA

 
BACKGROUND/SUMMARY:


The Limekiln Road Bridge Replacement Project is funded by the Federal Highway Administration’s Highway Bridge Program (HBP). The existing 14.1-foot wide bridge was deemed structurally deficient, prompting replacement with a new 41-foot long, 35.5-foot wide structure that meets current design standards and provides two 12-foot lanes with 4-foot shoulders. A temporary detour is being used during construction.

 

On June 18, 2024, the Board awarded a $2,961,378 construction contract to Granite Rock Company.

 

To support RMA Public Works staff in managing the construction contract and overseeing construction activities in accordance with Caltrans and FHWA guidelines, the Board approved a $574,173.70 contract with CM PROS on June 4, 2024, for construction contract administration, engineering, inspection, materials testing, and environmental permit compliance services.

 

Construction was originally scheduled to begin in July 2024 but was delayed due to environmental constraints and permit requirements. Work ultimately started in August 2025.  These delays, combined with added environmental compliance requirements and the need to expedite work within the one-season window, have required CM PROS to complete tasks beyond the original scope. On February 24, 2026, the board approved Amendment #1 to increase the contract amount by $462,285.78, for a new total not to exceed $1,036,459.48.

 

Amendment # 2 is required to extend the contract term through June 30, 2027 with no changes to the Cost or Scope of the original contract. Since the project is 100% reimbursable under FHWA’s HBP, reimbursement funds will be requested through Caltrans. CMPROS is contracted to oversee only one project for the County which is the Limekiln Road Bridge Replacement Project.

 

CM Pros - Limekiln Road Bridge - Construction Management Services (RMA-2027-000-01)
Contract Additional Amt Total Amount Expiration Date Approved By Approval Date Reason for Contract / Amendment
Original   $574,173.70 12/31/2026 BOS 06/04/2024 Construction contract administration, engineering, inspection and environmental compliance
Amendment # 1 $462,285.78 $1,036,459.48 12/31/2026 BOS 02/24/2026 Extended pre-construction services and environmental monitoring requirements (CDFW)
Amendment # 2 $0.00 $1,036,459.48 12/31/2027 BOS (11/17/2026) Term Extension Only
 
FISCAL IMPACT:


Limekiln Road Bridge Replacement Project is budgeted for $50,000.00 for FY2026-2027.

Since there are no changes to the contract cost, there will be no impact to the previously approved budget.

This project is 100% reimbursable under FHWA’s HBP and reimbursement funds will be requested through Caltrans.

The Budget Line Item # is 210.70.2020.1211.650.201

 

 
STAFF RECOMMENDATION:


1. Approve Amendment #2 with CM PROS to extend the contract term through June 30, 2027 with no changes to scope or cost to provide construction contract administration, engineering, inspection and environmental compliance services for the construction of the PWB-2402 Limekiln Road Bridge Over Pescadero Creek Bridge Replacement Project – Federal Aid Project No. BRLO-5943(063);  and
2. Authorize the Chair, County Executive Officer, or designee to execute the contract amendment.

 
ATTACHMENTS:
Board Agenda Fact Sheet - CM PROS Amendment #2
RMA-2027-000-01 - CM Pros - AM 2 - Limekiln Road Bridge - CM Services - Exp. 06.30.27