AGENDA ITEM NO. 6.s
 

Item Cover Page

 
 
 
 
CITY COUNCIL MEETING AGENDA ITEM REPORT
 
DATE:
October 14, 2026
 
SUBMITTED BY:
Jean Totti, Public Works & Utilities
 
ITEM TYPE:
Resolution
 
AGENDA SECTION:

CONSENT AGENDA

 
SUBJECT:

Change Order No. 5 with NDC Construction Company for the Bradenton Police Department Headquarters

 
SUGGESTED ACTION:

Approval

 
Is this item Quasi-Judicial?
No
 
Does this item require a public hearing?
No
 
EXPLANATION:

Change Order No. 5 to the construction contract with NDC Construction Company for the Bradenton Police Department Headquarters increases the contract by $100,266.50, from $29,889,406.56 to $29,989,673.06. The revised total remains below the original awarded contract amount of $33,904,806.89.


The change order covers additional disposal of contaminated soils, revised site modifications to address unexpected conditions, and additional labor and materials for power, data, and communications systems to equip the building with the latest technology.

 
FINANCIAL IMPACT:

The change order increases the contract by $100,266.50, bringing the revised contract total to $29,989,673.06.

 
ATTORNEY REVIEW/RECOMMENDATION:

Approved by Legal.

 
SUGGESTED MOTION:

Motion to approve Change Order No. 5 for the Bradenton Police Department Headquarters. 

 
ATTACHMENTS:
Change Order No. 5