Grant Agreement 27SRP03 with the Florida Department of Environmental Protection (FDEP) for the Lift Station 08 Relocation
Approval
No
No
Grant funding will reimburse the City for construction services, which include demolition of existing Lift Station 08 and building a new submersible pump station approximately 9 feet higher in elevation located at 1310 4th Ave. W. The new Lift Station 8 will be constructed to exceed minimum flood-resistant construction standards of the Florida Building Code and FEMA floodplain requirements, with the wet well built above the 100-year floodplain elevation and critical electrical equipment and bypass pump systems elevated an additional 1.5 feet.
Through State Appropriation Grant, the City will be reimbursed up to $3,000,000 for the reconstruction of LS08 (50% match). The City will match $2,000,000 using impact fees.
Reviewed by Attorney Rudacille.
Motion to approve Grant Agreement 27SRP03 with the FDEP.