AGENDA ITEM NO. 6.l
 

Item Cover Page

 
 
 
 
CITY COUNCIL MEETING AGENDA ITEM REPORT
 
DATE:
September 23, 2026
 
SUBMITTED BY:
Nicholas Toth, Purchasing
 
ITEM TYPE:
Agreement
 
AGENDA SECTION:

CONSENT AGENDA

 
SUBJECT:

Partial Guaranteed Maximum Price (GMP) Amendment to Agreement for Construction Management at Risk (CMAR) Services for WRF Equalization Tank with TLC Diversified, Inc. 

 
SUGGESTED ACTION:

Approval

 
Is this item Quasi-Judicial?
No
 
Does this item require a public hearing?
No
 
EXPLANATION:

The City of Bradenton and Construction Manager (TLC Diversified, Inc.) entered into the Agreement for Construction Management at Risk Services for Water Reclamation Facility Equalization Tank Project under which Construction Manager is providing the professional construction management services requisite to the implementation of the construction of the Equalization Tank. The Construction Manager and Owner have agreed upon a Partial GMP encompassing all costs for early work demolition of the temporary Equalization Tank while we await submission of the finalized GMP for construction of the new Equalization Tank. 

 
FINANCIAL IMPACT:

Funded through the General Fund.

 
ATTORNEY REVIEW/RECOMMENDATION:

Reviewed and approved by Attorney Rudacille. 

 
SUGGESTED MOTION:

Motion to approve the Partial GMP Amendment to Agreement for CMAR Services for the WRF Equalization Tank with TLC Diversified, Inc.

 
ATTACHMENTS:
Partial GMP Amendment with TLC Diversified, Inc.