I move to approve the Contract as presented.
May 13, 2026 (Item 5.B) – The Regional Transportation Commission (“RTC”) approved projects in District 4 for Fiscal Year 27, which included the Project.
The Project is located in Performance District 4 and will perform full depth reconstruction on 5th Street
between Division Street and Thompson Street, Mill and overlay on 5th Street between Terrace Street and Mary Street, Terrace Street between Patton Street and 5th Street, Curry Street between 10th Street and 6th Street, and 10th Street between Division Street and Carson Street. All segments will include ADA upgrades and sidewalk where appropriate. The City is also replacing or extending water lines in Curry and 10th Streets, and extending or replacing sewer lines in 5th and Curry Streets. The Project was identified and approved by the RTC in May 2026 as part of the District 4 Pavement Prioritization process, which evaluated regional and local roads based on several factors, including road condition, classification, safety, and other relevant criteria.
Wood-Rogers was selected using the city’s Statement of Qualifications list. If approved, the Project is scheduled to begin design in September 2026 and will reach the 100% design review in spring of 2027, with advertisement for bids planned in summer or fall of 2027. The Contract not-to-exceed total is $369,500.
District 4 - Curry, Division, 5th, 10th Rehabilitation Project No. P303527004, Regional Transportation Fund, Capital Improvements account / 2503035-507010.
District 4 - Curry, Division, 5th, 10th Rehabilitation Project # P303527004. If approved, the Regional Transportation Fund, Capital Improvements account, 2503035-507010, with a current budgeted amount of $1,022,188, will be reduced by $304,500; and the Water Fund, Capital Improvements account 5203505-507010, with a current budgeted amount of $65,000, will be reduced by $65,000.
Do not approve the Contract and provide an alternative direction to staff.