Bozeman City Logo

Memorandum


REPORT TO:

City Commission

 

FROM:

Shawn Kohtz, Director of Utilities

Brian Heaston, Engineer III

 

SUBJECT:

Resolution Establishing the Unit Cost for Payment of Cash In Lieu of Water Rights

 

MEETING DATE:

November 10, 2026

 

AGENDA ITEM TYPE:

Resolution

 

RECOMMENDATION:

I move to approve the Resolution establishing the unit cost for payment of cash in lieu of water rights.

 

STRATEGIC PLAN:

6.1 Clean Water Supplies: Ensure adequate supplies of clean water for today and tomorrow.
 

BACKGROUND:

Resolution 4095, passed March 17, 2008, establishes the City’s current cash in lieu of water rights (CILWR) unit cost at $6,000/acre-foot. New developments must satisfy the City’s water adequacy code, set forth at Sec. 40.02.1500 Bozeman Municipal Code (BMC) as of November 22, 2026, prior to final development approval. (Note, the water adequacy code is also found at Sec. 38.410.110 BMC, which City Staff intends to amend to reference Sec. 40.02.1500 BMC during the next round of Ch. 38 cleanup amendments.)  Code compliance may occur through the transfer of municipal water rights to the City, by payment of CILWR, or a combination thereof. Compliance through payment of CILWR to offset a development’s municipal water use has been the primary compliance method chosen by the vast majority of development applicants because the alternative method of obtaining municipal water rights under state law is highly complex, takes multiple years to complete, and has no guaranteed outcome. The code requires CILWR payments to be made at the CILWR rate effective on the date of payment is provided to the City.

 

The City established its first water adequacy policy in 1984 following the loss of the Mystic Lake water supply when the Mystic Lake dam was breached due to public safety concerns. The original water adequacy policy was set forth in Section 2.2 of Resolution 2502, which established the City’s annexation policy at the time. The policy required the transfer of water rights to the City to offset ethe anticipated water demands at full development of the annexed property. The allowance for payment in lieu of a water rights transfer was part of the original water adequacy policy. This policy framework is in place today but has seen modification of its implementation details and codification structure to keep pace with changing water use patterns, water market forces, and state law.

 

Technical and economic analyses supporting an updated CILWR unit cost have been performed and summarized in the attached CILWR update study. The report recommends increasing the unit cost to the $13,050/acre-foot midpoint of the $11,600 - $14,500 range derived by the 3-pronged valuation methodology explained in the attached report. This work was completed by WestWater Research as a specialty subconsultant to the City’s on-call water rights consultant, HydroSolutions. WestWater Research is an industry leading water economics firm specializing in water rights valuations, water markets, and transactional support throughout the western U.S.

 

The attached Resolution describes the limited purposes for which CILWR revenues may be expended. Notably, CILWR revenues are generally limited to funding costs associated with water rights acquisitions and administrative water rights changes. CILWR revenues cannot be utilized to fund infrastructure investments needed to beneficially use the water rights that are acquired with CILWR.  The City’s water impact fees are purposed for the necessary infrastructure complement.

 

UNRESOLVED ISSUES:

The Community Development Board (CDB) at its October 19, 2026 meeting received a special presentation of the CILWR update report findings and recommendations. No formal action was requested or taken by CDB on the matter of updating the CILWR unit cost. The CDB expressed concern about the magnitude of the increase and suggested the City Commission consider stepping into the recommended $13,050/acre-foot unit cost target incrementally, as well as delaying the effective date for the increase to provide time to conduct stakeholder outreach.

 

There are three primary decision points for the City Commission in establishing an updated CILWR unit cost: 1) establishing the updated unit cost target; 2) whether the target is stepped into incrementally or in one jump; and 3) the date the target becomes effective. The attached Resolution has been prepared by City Staff to establish the CILWR unit cost at the recommended amount of $13,050/acre-foot, in one jump, with the effective date occurring on November 23, 2026.

 

If the City Commission decides any of the three decision points differently than expressed in the Resolution, City Staff requests the Commission clearly articulate each decision point through separate motion, discussion and vote in order for Staff to prepare the Resolution accordingly prior to the Resolution’s execution by the Mayor.

 

ALTERNATIVES:

As suggested by the City Commission.

 

FISCAL EFFECTS:

The recommended CILWR fee midpoint of $13,050/acre-foot is over double the current fee rate of $6,000/acre-foot.  1 acre-foot of water can serve approximately 4 single family homes or approximately 8 multi-family units.

 

 

Attachments:

 
Resolution Establishing the Unit Cost for CILWR.pdf
Bozeman CIL Update_FINAL-2026.10.01.pdf
 

Report compiled on: October 29, 2026