Griffin Nielsen, Water Resource Engineer
Shawn Kohtz, Director of Utilities
Authorize the City Manager to sign Task Order 1 of the Professional Services Master Task Order Agreement with Advanced Engineering and Environmental Services, LLC, for the Water Treatment Plant Tank Influent Level Control Project
Authorize the City Manager to sign Task Order 1 of the Professional Services Master Task Order Agreement with Advanced Engineering and Environmental Services, LLC, for the Water Treatment Plant Tank Influent Level Control Project.
The Water Treatment Plant (WTP) tank is a partially buried 5.2-million-gallon concrete water storage tank located adjacent to the City’s Sourdough WTP. The tank provides finished water storage and operational flexibility for the City’s Water Utility. There is a hydraulic constriction that limits storage depth in the tank. This project will remove this operational constraint by installing a standpipe on the tank's influent line, allowing for full operational flexibility and increased system reliability.
Advanced Engineering and Environmental Services, LLC (AE2S) provides professional engineering services on an on-call basis for Bozeman’s Water Treatment Division under a Master Task Order Professional Services Agreement, authorized by the City Commission on April 15th, 2025. AE2S completed the evaluation of the operational constraint and identified the project as part of the ongoing Sourdough Water Treatment Facility Plan. Attached is Task Order 1, which provides design and bidding support services for the WTP Tank Influent Level Control Project.
None
As suggested by the Commission
Task Order 1 has a total cost of $58,400. Funding will be provided from the CIP No. W171 project budget, set at $300,000 in FY27; as such, adequate funding exists.