City Commission
Nick Pericich, Superintendent Water/Sewer Operations
Shawn Kohtz, Director of Utility Department
Authorize City Manager to Sign Agreement with Echologics LLC to provide a Leak Monitoring System for City Water Distribution Mains
November 17, 2026
Agreement - Vendor/Contract
Authorize the City Manager to sign the agreement.
Currently, the City relies on a combination of a manual leak detection survey program and inbound customer calls to identify water distribution main leaks and/or bursts. The entire water distribution system is currently surveyed manually approximately one time each year (spread out through the year). In the past, the City has deployed its manual leak monitoring system to reduce instances of water leaks going undetected for an extended period of time and conserve the City's water resources, unplanned customer outages from pipe breaks, and damage to other infrastructure nearby to water pipes. A request for proposals was issued to select an automated leak detection system to replace the current manual method of leak detection, and Echologics LLC was selected as the most qualified candidate. The Echologics system uses acoustic leak detection with devices that attach to fire hydrants, "listens" for water main leaks nightly, and reports the results to City staff via an automated system. The City initiated a pilot project with Echologics LLC over the past year, and the pilot has been successful to date. Acoustic detectors were installed on approximately 3 percent of the City's water distribution system. In the three-month pilot period, there was an estimated return on investment of approximately $127,000. There were 12 leaks found and repaired during that time frame. This agreement will allow us to continue to use the existing pilot system with future plans of a larger system-wide deployment planned several years out in the capital plan.
None
Return to manual leak detect procedures and check water mains once per year.
The approximate annual fee for this system is currently about $10,000 for the cellular service and monitoring. This has been accounted in the operating budget.