STAFF REPORT

 
 
TO:
CITY COUNCIL
 
FROM:
Elizabeth Gibbs, City Manager
 
PREPARED BY:
Nate Smith, Deputy Director of Public Works/City Engineer
Art Vela, Director of Public Works
 
MEETING DATE:
September 8, 2026
 
SUBJECT:

Accept as Complete Various Improvements Related to the Atwell Specific Plan Development and Authorize a 90% Reduction of the Improvement Bonds and Exoneration of Monumentation Bonds

 

STAFF RECOMMENDATION:

City Council accept as complete various improvements related to the Atwell Specific Plan Development and authorize a 90% reduction in the improvement bonds and exoneration of Monumentation Bonds.

BACKGROUND:

On May 24, 2024, City Council adopted Resolution 2024-77 approving Final Tract Map 37388-4, authorizing staff to sign the map and subdivision improvement agreements, release the map for recordation, and accept the performance and labor and material bonds for public improvements. 

 

As conditions of approval for the Atwell Specific Plan development, Tri Pointe Homes was required to sign subdivision improvement agreements and to submit bonds to assure the City that the required public improvements are constructed according to City standards and specifications. These public improvements include onsite street, sewer, water, and non-potable water.

JUSTIFICATION:

Staff has verified through inspections that the required public improvements were completed per City standards and specifications and recommends that City Council accept the improvements as complete and authorize the 90% bond reduction for the following bonds:

 

Bond #

Bond Amount

Improvements

30219395

$107,489.04

TR37388-4 Apex Street 2B On-site Water Improvements

30219396

$63,577.51

TR37388-4 Apex Street 2B On-site Non-Potable Water Improvements

30219394

$282,008.52

TR37388-4 Apex Street 2B On-site Street Improvements

30219409

$1,381,560.68

TR37388-4 PA14-1 Street Improvements

30219410

$566,341.89

TR37388-4 PA14-1 Water Improvements

30219411

$586,061.53

TR37388-4 PA14-1 Sewer Improvements

 

The remaining 10% of the bond amounts will remain for a period of 12 months (maintenance period) at which point the 10% balance will be released and the improvements will become City owned and maintained improvements.

 

Staff has verified through inspections that the required public improvements were completed per City standards and specifications and recommends that City Council accept the improvements as complete and authorize the 100% bond exoneration for the following bonds:

 

Bond #

Bond Amount

Improvements
30219412         $37,924.68 TR37388-4 PA14-1 Monumentation 
FISCAL IMPACT:

Not Applicable

ATTACHMENTS: