2025/26 STORMWATER EROSION CONTROL PROGRAM
(WORRELL CREEK)
The Stormwater Erosion Control Program is an annual program for the stabilization of areas that have become eroded in streams, channels, swales, gullies, or drainage ways that are part of the City’s stormwater system. This project involves the realignment and stabilization of Worrell Creek along Mortensen Parkway and west of University Boulevard to protect sanitary sewer infrastructure that runs along the stream corridor. Work will take place on City property at Carroll Marty Disc Golf Course Park and on ISU property.
Plans and specifications for this project were completed by Bolton & Menk. Construction is anticipated to be completed in one stage over a single year. The impacts to the parks property were coordinated with staff from the Parks and Recreation Department. Access to the Disc Golf Course will be maintained throughout the duration of construction with interruptions to a few holes on the course. Fencing is included to keep children and other park users out of the construction areas. Construction access to the project will be from designated areas on Mortensen Road and University Boulevard. The Disc Golf Course will be returned to existing conditions upon completion of the project.
City staff also coordinated with Iowa State University (ISU) staff to ensure its concerns and needs were incorporated into the project design where it occurs on ISU property. No nearby privately owned properties will be impacted by the construction activity.
A summary of revenues and projected expenses is shown below:
| Description | Revenue | Expenses |
| 2025/26 Stormwater Erosion Control Program (Stormwater Utility Funds) | $850,000 | |
|
Construction (Estimate) |
$731,963 |
|
| Engineering/Administration (Overall Program) | _________ | 118,037 |
| TOTAL | $850,000 | $850,000 |
- Approve plans and specifications for the 2025/26 Stormwater Erosion Control Program (Worrell Creek) project, setting January 6, 2027, as the bid due date and January 12, 2027, as the date of Public Hearing.
- Do not approve this project.
Approval of the plans and specifications will continue to keep this project on the January 6, 2026, letting schedule. This project will prevent further erosion from occurring within the stream and prevent future damage to the sanitary sewer. Therefore, it is the recommendation of the City Manager that the City Council adopt Alternative No. 1 as described above.