TECHNICAL SERVICES COMPLEX HVAC IMPROVEMENTS PROJECT
The Technical Services Complex (TSC) houses the Water Meter Division and Laboratory Services Division. In February 2026, the City Council approved a professional services agreement for design services associated with the renovation of the TSC. The original project scope included HVAC system improvements, interior finish updates, lighting upgrades, building accessibility improvements, and other building renovations.
As design progressed, staff evaluated project costs against available funding and determined that it would be prudent to proceed with the HVAC improvements as a standalone project at this time. The HVAC work addresses the most pressing building needs and is necessary to replace aging and failed heating, ventilation, and air conditioning equipment. Architectural renovations and other building improvements originally included in the project have been deferred and will be evaluated and prioritized separately through future capital improvement planning efforts.
| BIDDER | BID AMOUNT |
|
Core Construction Services, LLC Des Moines, IA |
$1,260,000 |
|
Story Construction Ames, IA |
$1,268,700 |
|
All Iowa Mechanical Des Moines, IA |
$1,430,200 |
|
Engineer's Estimate |
$1,570,878 |
- Accept the report of bids and reject all bids.
- Accept the report of bids, approve the final plans and specifications (without the addendum), and award a contract to Core Construction Services, LLC, of Des Moines, IA, in the amount of $1,260,000.
- Accept the report of bids, approve the final plans and specifications, and award a contract to one of the other two bidders.
- Do not award a contract at this time.
Staff received a very late addendum to the specifications that did not allow time for proper review and distribution. The addendum was distributed by the consultant to some, but not all prospective bidders outside of the City’s official bidding process, creating the potential for unequal access to project information and an inconsistent scope of work being assumed by bidders.
Rejecting all bids and restarting the project will ensure a fair, transparent, and competitive bidding process for all prospective bidders. Staff will confer with the design consultant and determine the best manner in which to proceed with the issuance of a new invitation to bid.
Therefore, it is the recommendation of the City Manager that the City Council approve Alternative No. 1, as described above.