WATER POLLUTION CONTROL FACILITY NUTRIENT REDUCTION MODIFICATIONS PHASE 1 PROJECT - CHANGE ORDER #13

 
BACKGROUND:

On August 13, 2024, City Council awarded a contract to Woodruff Construction for modifications to the Water Pollution Control Facility (WPCF) in the amount of $53,370,000. These modifications are the first of two construction phases that will ultimately enable the facility to achieve the goals of the Iowa Nutrient Reduction Strategy.

 

As is common with large construction contracts, this project has required multiple change orders. To date, 12 change orders have been approved for a combined total adjustment in the contract price of $242,457.22. Details regarding the scope and amounts of each change order are outlined below in Table 1.

 

A 13th change order has been prepared and is ready for Council approval. It contains two items. The first (an increase of $86,606.23) is to modify and expand the electrical infrastructure serving the North Building Complex. This item was requested by City staff. The electrical contractor already on-site has the electrical manhole and trenching associated with this area open as part of the ongoing project. 

 

The adopted FY 2026/27 CIP includes $50,000 to perform this work. Staff will reduce that during the mid-year budget adjustment, retaining $20,000 for City staff to finish the electrical work in the north buildings. The second component of the change order is a credit (-$4,482.60) associated with replacing a planned section of concrete gutter with asphalt gutter near the Sludge Pumping Building. This revision was requested by City staff to improve snow removal operations and ongoing maintenance activities. The asphalt gutter will continue to provide the required drainage function while better accommodating maintenance equipment.

 

Table 1: Change Order Summary

Change Order #1 

Credit for Enviromix, fire alarms, canopy; reroute gate power circuit; expansion joint changes.

(231,878.79)

Change Order #2

Modifications to the ceiling and lighting in portions of the Administration Building.

(25,280.00)

Change Order #3

Changes to Control Box A & B; changes to framing elements, reimbursement for special inspections.

10,835.86

Change Order #4

Changes to door framing; changes to ceiling tiles; changes to electrical outlets; additional painting requested by staff.

13,459.25

Change Order #5

Changes to valves & piping in Structure 10; changes to reinforcing and electrical at Structure 20; add booster fan; casework changes in admin building; add (2) well supply tanks and well control modifications; Deletion of gate valve in Control Box A (later restored as part of Change Order #9); misc changes in Structure 20.

(40,743.03)

Change Order #6 

Integrate doors into fire alarm in Admin; change paving to PCC for (8) parking stalls; credit for brass tags vs stainless; credit for rehab slide gate valves in Structure 10 versus replacement; Structure 200 berm elevation changes; corner guards in Structure 200; changes to the 4" DCW line near the RWPs.

$71,844.57

Change Order #7

Add asbestos and lead abatement for demolition of old admin building; add remote control for trolley hoist; misc electrical changes; add door holder/closer; extend water line in grit building; additional fencing; removal of unknown foundation under old admin building; add additional wireless access points.

$44,527.37

Change Order #8 

Relocate overhead door; door hardware change; credit from water line relocation; door opener to Room 20012; add corner guards in admin building; substitute PLC type.

$3,843.61

Change Order #9

Credit for eliminating crimp connectors; install water supply, drain, and install owner-supplied sink in shop; credit for eliminating hangers on energy recovery unit duct; remove and replace gate door in Control Box A.

$81,739.80

Change order #10

Supply and install (6) new VFDs for the Raw Wastewater Pumps, add (4) load transfer plates, credit for expansion joint material change, no-cost correction to Change Order #9.

$230,920.52

Change Order #11

Remove and replace flow meter FM-8; remove and replace pinch valve PHV-03; install new plug valve ahead of PHV-03; supply owner-installed float switch for Disinfection Building ERW; credit for substituting HDPE tees in lieu of ductile iron tees around Structure 80; provide and install 30 lf of sidewalk adjacent to Structure 10.

$55,909.91

Change Order #12

Remove an existing 3-way plug valve and replace with 8-inch glass lined ductile iron cross fitting; deduct credit for eliminating painting in grit loadout area.

$27,278.15

Change Order #13 - this action

Electrical system repairs to the north building complex; substitute HMA curb and gutter sections in place of concrete near the Sludge Pumping Building.

$82,123,63

Total Approved Change Orders (Including this action)

Percent of Original Contract

$324,580.85

0.61%

 

 

 

Table 2 below summarizes the overall project budget.

 

Table 2: Total Project Funding & Expenses

  Funding Expenses
Prior Years    
   FY 2023 1,000,472  
   FY 2024 1,438,643  
   FY 2025 18,573,090  
   FY 2026 (Preliminary) 26,608,806  
   FY 2027 (Includes pending carryovers)

15,018,184

 
WTFAP Grant - Iowa Finance Authority 500,000  

Engineering

 

6,038,000

Construction    
   Original Contract   53,370,000
   Change Order #1    (231,878)
   Change Order #2   (25,280)
   Change Order #3    10,836
   Change Order #4    13,459
   Change Order #5   (40,743)
   Change Order #6    71,845
   Change Order #7   44,527
   Change Order #8   3,844
   Change Order #9   81,380
   Change Order #10   230,921
   Change Order #11   55,910
   Change Order #12   27,278
   Change Order #13 - this action  

82,124

Owner Allowance (furnishings, etc.)   400,000
All Other Expenses   122,675

TOTAL

63,139,195

60,254,898

Remaining Available Contingency

  2,884,297

 

The cost of the electrical work in Change Order #13 will be partially offset by the $30,000 reduction in the CIP project described above.  The remaining expense will come from the project contingency.

 

It should be noted that the SRF program is a reimbursement program, meaning that the City first spends the money, then the program reimburses for eligible expenses. This method ensures the City will only borrow for expenses the City Council has authorized and are necessary to complete the project, thus minimizing interest expense associated with the improvements. 

 

 

 

 

 

ALTERNATIVES:
  1. Approve Change Order #13 to the contract with Woodruff Construction for the Water Pollution Control Facility Nutrient Reduction Modifications Phase 1 Project in the amount of $82,123.63.
     
  2. Do not approve the change order. This would reject the recommended changes to the contract documents.  
CITY MANAGER'S RECOMMENDED ACTION:

The proposed changes are to maintain and improve the reliability and function of the Water Pollution Control Plant Modifications. The consultant, contractor, and City staff have worked closely together to come up with reasonable, cost-effective recommendations. Therefore, it is the recommendation of the City Manager that the City Council adopt Alternative No. 1 as described above.

ATTACHMENT(S):
CO13 w Encl.pdf