ITEM #:
30
 
DATE:
10-13-26
 
DEPT:
PW
 

COUNCIL ACTION FORM

SUBJECT:

2026/27 AIRPORT AIRSIDE IMPROVEMENTS PROJECT (RECONSTRUCTION OF RUNWAY 01/19)

 
BACKGROUND:

The City has a Master Agreement with Bolton & Menk, Inc., of Ames, IA, for engineering services at the James Herman Banning Ames Municipal Airport. Recent work has included the design, final plans, and bidding for the Reconstruction of Runway 01/19. With design complete and construction about to begin, two amendments to the Master Agreement are needed for the construction phase engineering services.

Amendment No. 1 – AGIS Design Survey ($114,200, lump sum). In May 2025, the Federal Aviation Administration (FAA) issued Engineering Policy 25-01, which updated its requirements for the Airports Geographic Information Systems (AGIS) survey program. Also, the Airport’s approach category is changing from “B” to “C” because of the higher approach speeds of aircraft already using the Airport. To meet the design standards for those aircraft, the Runway 01/19 profile must be flattened.

Together, these changes require an AGIS design survey, which the FAA uses to develop or amend instrument flight procedures. The work includes geodetic control, aerial photography, an aeronautical survey of the runway and navigational aids, and FAA-compliant mapping and data submittals. It is scheduled for September 2026 through March 2027.

Amendment No. 2 – Construction Phase Services ($2,098,400). This amendment provides the engineering services needed for the Reconstruction of Runway 01/19, project inspection and closeout. Construction observation includes a full-time Resident Project Representative (up to 3,894 hours), a second observer during critical operations (up to 2,130 hours), and up to 100 field visits by the project manager.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Service Amount Fee Type
Construction Administration $569,600 Lump Sum
Construction Observation $1,294,700 Hourly, Not-to-Exceed
Construction Testing $74,200 Cost Plus Fixed Fee, Not-to-Exceed
AGIS As-Built Survey $84,300 Lump Sum
As-Built Airport Layout Plan $39,400 Lump Sum
Construction Grant Application $3,600 Lump Sum
Construction Grant Closeout $32,600 Lump Sum
Total Amendment No. 2 $2,098,400  

 

The two amendments total $2,212,600. Both are eligible for FAA reimbursement of up to 95%. The estimated local share is $110,630 ($5,710 for Amendment No. 1 and $104,920 for Amendment No. 2). The approved project budget included an estimated $2,650,000 for these services. The two amendments come in $437,400 under that estimate, and the required local share is covered by the local funding already identified for the project.

The revised project revenues and expenses are shown below (the formatting of items in the table matches the FAA's :

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Fiscal Year Available Revenues Amount Revised Anticipated Expenses Amount
  Design Phase Design Phase
2024/25 Federal Grant - Design (95%) $1,140,095 PSA - Design $1,196,600
2024/25 Airport Improvements Fund $130,000 Design Independent Fee Evaluation (IFE) $3,500
  Construction Phase Construction Phase - FAA Grants 036/037
2025/26 Federal Grant 036 (95%) (accepted) $7,810,900 Administration/Legal/Advertisement $6,209
2026/27 Federal Grant 037 (90%) (anticipated spring 2027) $12,769,200 AGIS Design (Amendment No. 1) THIS COUNCIL ACTION $114,200
2024/25 Airport Improvements Fund (Reprogrammed) $25,000 End Fire Glideslope Design $75,000
2025/26 G.O. Bonds $531,750 Construction Services THIS COUNCIL ACTION $1,942,100
2026/27 G.O. Bonds $623,250 AGIS As-Built THIS COUNCIL ACTION $84,300
2026/27 G.O. Bonds (previously issued) $975,000 As-Built Airport Layout Plan THIS COUNCIL ACTION $39,400
2026/27 Airport Improvements Fund $42,500 Grant Closeout THIS COUNCIL ACTION $32,600
      Construction Contract - Runway 01/19 $19,118,791
      IFE - AGIS and Construction Services $10,000
      Glide Slope Refurbishment Kits $340,000
      Flight Checks $210,000
  Total Available Revenue $24,047,695 Revised Total Expense $23,172,700
  Available Revenue over Anticipated Expenses* $874,995

*Federal grant reimbursement is based on actual eligible costs. Because lower eligible costs also lower the federal share, the actual local savings will be less than the amount shown.

ALTERNATIVES:
  1. Approve the following amendments to the Master Agreement with Bolton & Menk, Inc., of Ames, IA, for the 2026/27 Airport Airside Improvements Project (Reconstruction of Runway 01/19):
    1. Amendment No. 1 for the AGIS Design Survey, in the lump sum amount of $114,200.
    2. Amendment No. 2 for Construction Phase Services, in an amount not to exceed $2,098,400.

  2. Do not approve the amendments. This would leave the City without the engineering services the FAA requires to administer, inspect, test and close out the grant-funded runway reconstruction, and to update the Airport’s AGIS data and Airport Layout Plan.

  3. Refer this item back to staff for further information.
CITY MANAGER'S RECOMMENDED ACTION:

The FAA requires these engineering services to administer, inspect, test and close out the federally funded runway reconstruction, and to update the Airport’s AGIS data and Airport Layout Plan. The fees are less than estimates included in the approved project budget and are eligible for 95% FAA reimbursement. Therefore, it is the recommendation of the City Manager that the City Council adopt Alternative No. 1 a-b, as noted above.

ATTACHMENT(S):
Task Order #7 Amendment No. 1 - AGIS Design Survey
Task Order #7 Amendment No. 2 - Construction Phase Services