2026/27 COLLECTOR STREET PAVEMENT IMPROVEMENTS (STATE AVE)
The Collector Street Pavement Improvements Program is an annual program for the reconstruction or rehabilitation of concrete streets in the Capital Improvement Plan (CIP). The 2026/27 program location is State Avenue from Mortensen Road to Arbor Street. State Avenue is anticipated to undergo full-depth concrete replacement with curb and gutter. The reconstruction of State Avenue was prioritized to address roadway needs prior to the completion of Fire Station #2. The project was moved up during the CIP development to be completed during 2027 in advance of the relocation of Fire Station #2 to State Avenue.
On July 14, 2026, City Council approved a Professional Services Agreement with Olsson of Des Moines, IA, for the 2026/27 Collector Street Pavement Improvements on State Avenue in the amount of $149,680. That contract did not include the design for the State Avenue and Mortenson Road intersection.
Amendment No. 1 in the amount of $6,430 was approved by staff. New sanitary main was added to the project to allow for Fire Station 2 to connect into the existing sanitary system. This amendment include survey for the design of the new sanitary main for the permanent easement agreement with Iowa State University.
Amendment No. 2 in the amount of $4,200 was approved by staff. This amendment includes advanced survey for the design of the State Avenue and Mortensen Road intersection.
Amendment No. 3 (this action)
During preliminary design, it was determined that a southbound turning lane is needed on State Avenue at the Mortensen Road intersection to help accommodate turning traffic volumes and emergency response vehicles. Adjusting the lanes and intersection geometry on the north side of Mortensen Road, along with including northbound turning on State Avenue for the south side of Mortensen Road, makes it practical to complete the entire intersection design now. Completing the full intersection design at this time provides three key benefits:
- Addresses the deteriorated condition of the existing pavement within the intersection.
- Keeps north and south access open through the intersection during future work planned CIP work along Mortensen Road.
- Minimizes future construction impacts on Fire Station 2 response times.
The proposed amendment to the professional services agreement with Olsson would complete the design of the State Avenue and Mortensen Road intersection in the amount of $45,065.
A summary of revenues and projected expenses is shown below:
|
Funding Source |
Revenues |
Expenses |
|
|
GO Bonds |
$2,800,000 |
|
|
|
|
|
|
|
|
Construction (East.) |
|
$2,300,000 | |
|
Engineering - Olsson PSA |
|
149,680 |
|
|
PSA Amendment 1 |
|
6,430 |
|
|
PSA Amendment 2 |
|
4,200 |
|
|
PSA Amendment 3 (this action) |
|
45,065 |
|
|
Administration |
|
294,625 |
|
|
TOTAL |
$2,800,000 |
$2,800,000 |
- Approve Amendment No. 3 to the professional services agreement with Olsson, of Des Moines, IA, for the 2026/27 Collector Street Pavement Improvements Program (State Avenue) in the amount of $45,065.
- Do not approve the amendment.
This amendment will allow for needed improvements to the State Avenue and Mortensen Road intersection to be completed with the State Avenue project. The need for the improvements became apparent as the design work progressed. Addressing the intersection improvements now will reduce the impact that turning traffic and emergency response vehicles experience upon completion of the State Avenue reconstruction. This improvement will also help reduce response times for emergency vehicles at the intersection. Therefore, it is the recommendation of the City Manager that the City Council adopt Alternative No. 1, as noted above.