RESOURCE RECOVERY AND RECYCLING CAMPUS CONSTRUCTION MATERIAL TESTING
The Resource Recovery and Recycling Campus (R3C) project represents a new method for handling solid waste, recycling, and yard waste for the City of Ames and partner agencies.
This project includes the construction of a new transfer station to receive, process, and transport solid waste to the City's new landfill partner in Carroll County. Additionally, the project will include a receiving area for recyclables that will then be transported to a material recovery facility and an area for yard waste collection. The new R3C facility will be located at 220 Freel Drive.
Following contract award, City staff solicited quotes from qualified firms in April 2026 for construction materials testing services for the project. A contract was awarded to Braun Intertec Corporation of Urbandale, IA in the amount of $48,793.50. Change Order No. 1 was approved by the City Council on May 26, 2026, in the amount of $3,668 to include material testing for onsite paving.
Due to the historically wet summer and fall in 2026, construction sequencing has had to be continually modified to ensure that progress is being made toward project completion dates. This modification in sequences has led to additional testing of subgrade material, reduced efficiency in the number of concrete pours, and additional trips and tests necessary for inspection and paving materials. These changes in the sequence have been made in an effort to stay on schedule with overall project, with completion ultimately still anticipated in Spring 2027.
While the sequence changes do not impact the construction costs, they do have an impact on the efficiency of the construction material inspections and testing necessary to support the project. As such, additional trips and material testing are necessary. The added scope is proposed in Change Order No. 2 in the amount of $38,928.50.
This added scope of work will increase the overall expense to $91,390, which requires City Council approval in accordance with Purchasing Policy. There is funding available within the existing project budget to support this additional material testing expense.
A revised project budget is provided below:
|
Budgeted Revenues |
Budgeted Expenses | ||
| Revenue Abated G.O. Bonds | $22,006,730 | Land Acquisition (220, 306, 312, 318, 400 Freel Drive) | $1,077,500 |
| Fleet Services Reserve Fund | 425,000 | Due Diligence prior to closing |
15,465 |
| FY 2025/26 Stormwater Quality Improvements CIP | 159,077 | Conceptual Design and Financial Modeling |
50,000 |
| Electric Services Rebate |
3,000 |
Final Design |
965,715 |
|
Solid Waste Alternatives Program (SWAP) Grants |
100,000 |
Final Design Contingency (revised) |
58,610 |
|
|
|
Permitting |
36,930.85 |
|
|
|
Builder's Risk Insurance |
25,444 |
|
|
|
Construction Contracts (as bid) |
$19,619,767 |
|
|
|
Previously approved change orders |
(1,358,109.12) |
|
|
|
Construction Incentives |
100,000 |
|
|
|
Items by Owner (FFE/Cameras/Fiber Network/Tree Clearing) |
266,600 |
|
|
|
Construction Contingency |
337,556.97 |
|
|
|
Construction Inspection (revised) |
91,390 |
|
|
|
Construction Manager Fee (Fixed fees plus 2.25% of contract amounts) |
958,927.30 |
|
|
|
Construction Manager General Conditions Costs (est.) |
448,000 |
|
R3C Construction Revenue Subtotal |
$22,693,807 |
R3C Construction Subtotal |
$22,693,807 |
|
Electric Utility Fund |
$2,340,000 |
Mobile Equipment - New Transfer Trucks (6x) (actual) |
$1,230,384 |
|
G.O. Bonds |
$975,000 |
Mobile Equipment - New Transfer Trailers (7x) (actual) |
942,585 |
|
Unobligated G.O. Bonds |
225,000 |
Mobile Equipment - Used Transfer Trailers (3x) (est.) |
180,000 |
|
Water Utility Fund |
40,000 |
Freel Drive Paving (as bid + contract admin) |
$1,102,310 |
|
|
|
|
|
|
Total Project Revenues |
$26,273,807 |
Total Project Expenses |
$26,080,804.03 |
- Approve Change Order No. 2 with Braun Intertec Corporation, of Urbandale, IA, in the amount of $38,928.50.
- Direct staff to pursue other alternatives to provide construction material testing services for the R3C project.
The addition of this scope of work to Braun Intertec allows for the most cost-effective means to provide these critical construction material testing services. The project sequencing has been modified to meet the overall project schedule and has led to the need for the additional testing scope. Therefore, it is the recommendation of the City Manager that the City Council adopt Alternative 1, as described above.