Notice of Completion for the Wetlands Edge Environmental Educational Enhancement Project (PR19-0100)
Accepting the Wetlands Edge Environmental Educational Enhancement Project (PR19-0100) as Complete and Authorizing the Public Works Director to File a Notice of Completion.
Erica Ahmann Smithies, P.E., Public Works Director
Ron Ranada, P.E., Senior Civil Engineer
David Miller, Capital Projects Coordinator
The Wetlands Edge Environmental Educational Enhancement Project (PR19-0100) constructed public-access and educational improvements, including pathways, a restroom and shade structure, landscaping, irrigation, and related site improvements.
The City entered into a construction contract with Marina Landscape, Inc. in the original amount of $679,065.95. Six Contract Change Orders totaling $103,410.39 were approved, resulting in an authorized construction contract amount of $782,476.34.
The one-year landscape maintenance period ended July 31, 2026. Following the final landscape review, the contractor completed all corrective work and remaining punch-list items. On October 5, 2026, City staff verified satisfactory planting establishment and completion of all remaining contract work.
The Project is complete and ready for formal acceptance. Upon acceptance, staff will proceed with recording the Notice of Completion and completing the remaining administrative closeout requirements.
Outdoors and Recreation: "Expand opportunities for use of outdoor recreation and an active and healthy lifestyle."
No additional appropriation or budget amendment is required for this action. The City has received the $250,000 State grant reimbursement associated with the Project.
| Description | Amount |
|---|---|
| Total Approved Project Budget | $950,000.00 |
| Total Project Expenditures | $933,176.44 |
| Remaining Project Budget Balance | $16,823.56 |
| Contract Item | Amount |
|---|---|
| Original Construction Contract | $679,065.95 |
| Approved Change Orders (Nos. 1–6) | $103,410.39 |
| Authorized Construction Contract Total | $782,476.34 |
Final payment and release of retention will be processed in accordance with applicable contractual and statutory requirements.
Level 0: No Further Public Communication Needed