CITY COUNCIL AGENDA
NOVEMBER 17, 2026

STAFF REPORT
BUSINESS
ITEM NUMBER: 10.
 


TITLE

Contract Award for Green Island Road Class I Trail (TR16-0704)


RECOMMENDATION

Adopt a Resolution awarding a Construction Contract to Martin Brothers Construction in the amount of $704,395 and authorizing the Public Works Director to approve and execute Contract Change Orders in an amount not to exceed the Project Budget in conjunction with the Green Island Road Class I Project (TR16-0704).


CONTACT

Erica Ahmann Smithies, P.E., Public Works Director


Ron Ronada, P.E., Senior Civil Engineer


BACKGROUND & ANALYSIS

The Green Island Road Class I Project (TR16-0704; "Project") is the final component of the Green Island Road Reconstruction and Widening Project (TR16-0700). When the Green Island Road Reconstruction and Widening Project was advertised for construction in the Spring of 2025, the Class I trail portion of the scope was omitted due to the delay of Caltrans authorizations for One Bay Area Grant Article 3 (OBAG) funding. Caltrans authorization was subsequently received to pursue the advertisement and construction of the Project.

 

The Project consists of constructing approximately 4,200 LF of new Class I multi-use trail, including a critical segment of the Napa Valley Vine Trail. The trail will be constructed on the north side of Green Island Road from Paoli Loop Road to Devlin Road. The Project will accommodate cyclists and pedestrians to encourage non-vehicular modes of transportation as required by local, regional and State Complete Streets policies. Additional traffic safety improvements include traffic signage and striping, and the installation of a high visibility thermoplastic crosswalk accompanied with a rapid rectangular flashing beacon for a crossing on Green Island Road at Paoli Loop Road.

 

The Engineer's Estimate for the construction of improvements is $1,193,000.00. On October 22nd, 2026, the following bids were received and publicly read aloud:

 

Bidder Total Bid Amount
Martin Brothers Construction $704,395.00
Argonaut Constructors $777,979.46
Zara Construction, Inc. $924,770.00
Redgwick Construction, Co. $937,400.00
Ghilotti Construction Company, Inc. $962,267.50
Coastside Concrete & Construction, Inc. $984,030.00
Imperial Construction & Engineering, Inc. $999,350.00
Dutch Contracting, Inc. $1,028,985.00
Kerex Engineering $1,059,000.00
Granite Rock Company $1,116,073.00
FBD Vanguard Construction, Inc. $1,181,443.00
Team Ghilotti, Inc. $1,191,417.00
Mission Constructors, Inc.  $1,475,596.50

 

The bid submitted by Martin Brothers Construction in the amount of $704,395.00 was the apparent low bid. Staff has reviewed the apparent low bid and found it to be both responsive and responsible. Staff has verified the contractor's qualifications including valid Class A license, DIR registration, and references, and found them to be satisfactory and acceptable. 

 

Staff recommends the Council award a Construction Contract to Martin Brothers Construction in the amount of $704,395 and authorize the Public Works Director to approve and execute Contract Change Orders in an amount not to exceed the Project Budget, in conjunction with the Green Island Road Class I Project (TR16-0704).


COUNCIL PRIORITY PROGRAMS AND PROJECTS
Transportation: "Improve the transportation network within the City to alleviate congestion and enhance the quality of life for the community."

FISCAL IMPACT

The FY 2026-27 Capital Improvement currently provides for the following Project Budget:

 

Fund Budget
OBAG 3 Grant (Fund 240) $1,000,000
Gas Tax (Fund 212)* $300,000
Total $1,300,000

 

*Gas Tax is a recurring annual revenue that is distributed by virtue of SB1. The annual revenue is about $300,000 annually. The $300,000 in Fund 212 will be used as the 20% of local grant funds to match the 80% of the $1,000,000 in previously awarded OBAG 3 (Fund 240). 

 

The estimated Construction Budget for construction of the improvements slated with the Martin Brothers Construction contract are as follows: 

 

Item Description  Estimated Cost
Construction Contract $704,395
Construction Contingency (15%) $105,660
Materials Testing Services $50,000
Staff $50,000
Total $910,055

 

Per the Project Budget, there are sufficient funds to cover the anticipated costs of construction. 

 

Additionally, in light of the reduced construction contract cost, City staff will try to increase the federal reimbursement percentage, with the goal of minimizing the use of local funds. 


ENVIRONMENTAL REVIEW

Pursuant to the California Environmental Quality Act (“CEQA”), an Initial Study/Mitigated Negative
Declaration (“IS/MND”), that includes a “Mitigation Monitoring and Reporting Plan (“MMRP”), was
prepared for the Project and circulated for 30 days star ng on August 27, 2019. A Notice of Intent
("NOI") to adopt a Mi gated Negative Declaration (“MND”) was posted at the County Clerk in
accordance with the CEQA requirements on August 27, 2019.


A public hearing for consideration of the Project and its IS/MND was noticed and held on October 1, 2019, before the City Council, which at that meeting determined 1) based upon the record that the
Project will not have a significant effect upon the environment if the mitigation measures listed in
the MND and MMRP are implemented; 2) adopted the IS/MND for the Project; 3) adopted the
MMRP for the Project, and 4) directed staff to file a Notice of Determination for the Project
consistent with the CEQA Guidelines. The IS/MND evaluated the separate actions the City will take
to complete the Project including the road work currently proposed.



COMMUNICATION
Level 2: Targeted Communication

There will be anticipated lane closures on Green Island Road during construction. Staff will work with the American Canyon Chamber of Commerce and City Communications Team on targeted outreach to the surrounding residents and businesses similarly to the process utilized for the Green Island Road Reconstruction and Widening Project. 